Buffalo Road Booster Pump Station Upgrade and Transmission Main
Owner
Project Type
Size
Project Overview
This project consisted of approximately 29,000 LF of a new 24-inch water main and the upgrade of an existing water booster station to a firm capacity of 6.5 MGD. CJS provided design, survey, easement mapping, permitting, and bid phase assistance for the project. The new booster pump station site consists of a prefabricated duplex packaged booster station, metering, pad-mounted standby diesel generator, electrical rack, and telemetry. The pump station design required extensive modifications to the existing structure to accommodate the larger pump skid system in an effort to minimize costs.